Improvements to the A194 (Leam Lane)

Aims and timeline

Overall, the work aims to: 

  • improve journey times travelling in and out of South Tyneside
  • improve the traffic flow when travelling in and out of South Tyneside
  • improve safety
  • reduce congestion
  • improve air quality

The improvements will also increase the efficiency of other nearby roads. 

Timeline

Work started in July 2021.

The works at Mill Lane roundabout and Roman Road slip road are expected to be completed by the end of July 2022. 

The remainder of work at Whitmare Pool Roundabout is expected to begin in late summer 2022, and should be complete by mid-September in time for the Great North Run.